ROAD CONSTRUCTION –WEEK OF 5-19-08
The
following projects are categorized by note in parentheses after the project name
as follows:
- (CIP) –
City Community Investment Program (Tel.
972-941-7152)
- (DEV)
– Private developer initiated (Tel. 972-941-7152)
- (PB. WKS.)
– City Public Works Department (Tel. 972-769-4142)
- (TxDOT) –
Texas Department of Transportation (Gus Khankarli,Tel.
972-542-2345)
- (PARKS)
– City Parks Department (Tel. 972-941-7235)
- (NTTA)
– North Texas Tollway Authority (Sherita Coffelt,Tel.
214-224-2398)
- (DAL.) –
City of Dallas ( Tel. 214-670-4262)
MAJOR CONSTRUCTION
ALERTS
DALLAS NORTH TOLLWAY BETWEEN
LBJ FREEWAY (I-635) AND WYCLIFF PLAZA (NTTA) – The North Texas Tollway Authority is
underway (as of July, 2006) with a major reconstruction project within these
limits. The project is expected to be underway for approximately two years
(until summer, 2008). For details, contact Sherita Coffelt, Assistant Public
Information Officer at the North Texas Tollway Authority. (Sherita Coffelt, NTTA
at 214-224-2398)
SH121 AT LEGACY DRIVE (TxDOT) –
Legacy portion of
the intersection was previously completed an opened to traffic. U-Turns remain
closed temporarily. (Jim May, TxDOT, 972-370-9722).
SH121 AT SPRING CREEK PARKWAY (TxDOT)
– Spring Creek
portion of the intersection was previously completed and opened to traffic.
U-Turns remain closed temporarily. (Jim May, TxDOT,
972-370-9722)
FULL ROAD CLOSURES (NO
TRAFFIC)
No
closures to report.
OTHER LANE
CLOSURES (EXCLUDING THOSE LISTED ABOVE)
15TH STREET DRAINAGE FROM
WEST OF US 75 TO COLUMBIA
PLACE (CIP) – Major storm drainage system installation in this area
will be underway. Various lanes east and west bound will be closed thru summer,
2008. Traffic should seek alternate routes if possible. (James
Caswell/Chris
Best)
15TH
STREET RECONSTRUCTION – AVENUE G TO AVENUE I (CIP) –
Paving work is
complete and all lanes of the road are opened to traffic. Periodic lane closures
will occur as utility companies do relocation work. (Dennis Freeman/Chris
Best)
COIT
ROAD AT MAPLESHADE (DEV) –
The left lane
northbound and the left lane southbound will be closed periodically for left
turn construction. (Dennis
Maloy)
DALLAS NORTH TOLLWAY – WINDHAVEN TO SPRING CREEK PKWY.
(DEV) – The
northbound right lane will be closed for storm sewer work (Rob
Hill).
HEADQUARTERS – PARKWOOD TO PRESTON (CIP) – Project includes widening from 4 to 6 lanes. One lane in
each direction will be closed for construction activity in the median between
7:00 am and 3:30 pm. Traffic may decide to seek alternate routes.
(Husain Hamza/James Powell)
LEGACY DRIVE BETWEEN CHASE
OAKS
BOULEVARD AND US 75 (DEV) – The north lane westbound will be closed.
(Walter
Ellwood)
LEGACY DRIVE – K AVENUE TO
CUSTER
ROAD (PB WKS) – Public Works is underway with pavement repairs on
Legacy. 1 lane eastbound from Custer to Red River will be closed for work and a
second lane will be closed between 9 am and 4 pm. 1 lane westbound from K Avenue
to Alma will be closed for work and a second lane will be closed between 9 am
and 4 pm. Motorists are advised to use alternate routes to avoid delays.
(Steve Spencer/Kioumar
Rezaie)
OHIO
DRIVE BETWEEN OLD SHEPHERDS WAY AND
PLANO
PARKWAY (PB WKS) - Street repairs on Ohio will begin the week
of May 12, 2008. One lane will be closed southbound for repairs. Traffic may be
detoured to the northbound side between 9 am and 4 pm to expedite construction.
Expect delays and use alternate routes. (Steve
Spencer)